Industrial Technology Decarbonization Pathways

EAF, H₂ Boilers, CCUS; CAPEX/OPEX/IRR; Scenarios

Board-level capital allocation models for major technology transitions (electrification, hydrogen, CCUS). Each pathway includes TRL, dependencies, grid impact, downtime, and IRR/NPV sensitivity to carbon pricing.

What it visualizes

  • current vs target state per asset class (steel, boilers, cement)
  • stranded-asset risk and book value exposure
  • CAPEX/OPEX deltas, IRR/NPV/payback, carbon cost avoided
  • grid reinforcement and renewable PPA requirements
  • scenario engine comparing conservative vs aggressive vs net-zero

Used for

  • board-level capital allocation decisions for technology transitions
  • validating technology readiness and dependencies
  • optimizing pathway selection based on carbon pricing sensitivity

Industrial Technology Decarbonization Pathways

Board-Level Capital Allocation Model – System Impact & Financial Analysis

Scenario Modeling

Transition 1: Blast Furnace Steel ProductionElectric Arc Furnace (EAF)

Current State

Blast Furnace Steel Production

Emissions2.4M tCO₂e/yr
Energy18,500 TJ/yr
Fuel TypeCoal + Coke
Stranded Asset Risk
Remaining Life12 years
Book Value€410M
Risk LevelHigh
Transition Architecture

Electric Arc Furnace (EAF)

Emissions380k tCO₂e/yr
Energy9,200 TJ/yr
Fuel TypeRenewable Electricity
Technology & Risk
TRL Level9 / 9
Execution RiskMedium
Supply Chain RiskLow
Financial Analysis
CAPEX
€680M
OPEX Δ
-€28M/yr
+€34M elec, -€62M fossil
IRR
14.8%
NPV
€420M
Payback
7.4 yr
Carbon Cost Avoided – Price Sensitivity
At €90/t
€181.8M/yr
At €120/t
€242.4M/yr
At €150/t
€303M/yr
Grid & Infrastructure Impact
Grid Demand+420 MW
% of Regional Capacity38%
Grid Reinforcement€220M
Renewable PPA Req.3,680 GWh/yr
Operational Impact
Water Impact
+420k m³/yr
Operational Downtime14 months
Workforce Change-420 roles, +180 new
Timeline2028–2032
Critical Dependencies
Grid reinforcement contract
Renewable PPA secured
EAF supplier selection
Industrial Competitiveness Impact
Before
€740/t steel
After
€610/t steel
Change
-17.6%

Transition 2: Natural Gas BoilerHydrogen Boiler

Current State

Natural Gas Boiler

Emissions820k tCO₂e/yr
Energy4,200 TJ/yr
Fuel TypeNatural Gas
Stranded Asset Risk
Remaining Life8 years
Book Value€124M
Risk LevelMedium
Transition Architecture

Hydrogen Boiler

Emissions42k tCO₂e/yr
Energy4,800 TJ/yr
Fuel TypeGreen H₂
Technology & Risk
TRL Level7 / 9
Execution RiskHigh
Supply Chain RiskHigh
Financial Analysis
CAPEX
€240M
OPEX Δ
+€18M/yr
+€32M H₂, -€14M gas
IRR
9.2%
NPV
€140M
Payback
9.8 yr
Carbon Cost Avoided – Price Sensitivity
At €90/t
€70M/yr
At €120/t
€93.4M/yr
At €150/t
€116.7M/yr
Grid & Infrastructure Impact
Grid Demand+180 MW
% of Regional Capacity16%
Grid Reinforcement€85M
Renewable PPA Req.1,580 GWh/yr
Operational Impact
Water Impact
+2.4M m³/yr
Operational Downtime6 months
Workforce Change-42 roles, +68 new
Timeline2027–2030
Critical Dependencies
Green H₂ supply contract (42k t/yr)
Electrolyzer capacity allocation
H₂ storage infrastructure
Pipeline connection
Industrial Competitiveness Impact
Before
€142/MWh
After
€168/MWh
Change
+18.3%

Transition 3: Cement Kiln – Fossil FuelCement Kiln + CCUS

Current State

Cement Kiln – Fossil Fuel

Emissions1.8M tCO₂e/yr
Energy8,400 TJ/yr
Fuel TypeCoal + Pet Coke
Stranded Asset Risk
Remaining Life15 years
Book Value€620M
Risk LevelVery High
Transition Architecture

Cement Kiln + CCUS

Emissions280k tCO₂e/yr
Energy9,100 TJ/yr
Fuel TypeAlternative Fuels + CO₂ Capture
Technology & Risk
TRL Level8 / 9
Execution RiskHigh
Supply Chain RiskMedium
Financial Analysis
CAPEX
€1.1B
OPEX Δ
+€54M/yr
+€68M CCUS, -€14M fuel
IRR
6.4%
NPV
€85M
Payback
12.2 yr
Carbon Cost Avoided – Price Sensitivity
At €90/t
€136.8M/yr
At €120/t
€182.4M/yr
At €150/t
€228M/yr
Grid & Infrastructure Impact
Grid Demand+320 MW
% of Regional Capacity29%
Grid Reinforcement€180M
Renewable PPA Req.2,800 GWh/yr
Operational Impact
Water Impact
+3.2M m³/yr
Operational Downtime22 months
Workforce Change-84 roles, +142 new
Timeline2029–2034
Critical Dependencies
CO₂ transport infrastructure
Storage site availability (EU ETS approved)
Environmental permit approval
CCUS subsidy confirmation
Industrial Competitiveness Impact
Before
€92/t cement
After
€114/t cement
Change
+23.9%

Scenario Simulation Engine – Risk-Return Analysis

MetricConservativeAggressiveNet-Zero 2035
Target Year204520382035
Total CAPEX€2.8B€4.2B€6.1B
Emission Reduction68%82%95%
Grid Dependency+620 MW+980 MW+1,420 MW
H₂ Demand42k t/yr85k t/yr124k t/yr
Annual Carbon Cost (2030)€184M€98M€42M
EBITDA Impact (2030)-€82M+€124M+€286M
Weighted IRR8.2%11.4%13.8%
CO₂ Breakeven Price€72/t€58/t€41/t